D A T E |
D E S C R I P T I O N |
August 01, 2003 |
Foundation wall forms partially constructed. |
| August
04, 2003 |
Forms completed. Foundation walls poured. |
| August 05, 2003 |
Foundation crew returned and removed concrete forms. |
| August
12, 2003 |
Earthwise Excavation returned to backfill the new foundations and install
foundation drainage pipes which are connected to gravel filled stormwater catch basins at
the rear of each home. |
| August 13, 2003 |
The initial framing began shortly after North City Lumber delivered two
truckloads of lumber. Construction of pony walls and installation of flooring joists
was almost completed on the north house. Most of the sill plates were installed on
the south house. |
| August
15, 2003 |
First wall erected on the north house and sub flooring almost complete.
South house joists complete and ready for sub flooring. |
| August
19, 2003 |
Framing continues on both homes. Two crews are working on the
framing, with the north home being a little further along at this point. Several
photos from Monday show how fast things are going up. |
| August
21, 2003 |
North City Lumber delivers another load of lumber. The north house
will likely see the second story walls completed on Friday. Meanwhile, the south
house team appears to be slacking... Evidently having way too much fun shooting
Gummy Bears with air operated nail guns :) |
| August
22, 2003 |
The bay window framing was completed on the south house which is almost
ready for second story joists. Two second story walls were completed on the north
house. Roof trusses for both homes will delivered after the Labor Day holiday. |
| August 29, 2003 |
Brian and his team continue to complete the remaining second story walls
on the south house. Fred Olsen and his crew who were working on the north house will
return next week to assist with installing the roof trusses. |
| |
|