The homes at 10033 42nd Avenue SW


- J u l y    2 0 0 3 -

D A T E

D E S C R I P T I O N

July 09, 2003   First day on the job site. Small excavator arrives. Clearing of grounds. Removal of fence.
July 10, 2003 Second day on site.  Continued clearing of grounds.
July 11, 2003 Day three.  Interior pictures after building materials recyclers removed salvageable materials. 
July 12, 2003 Saturday.  Brian takes down the garage. Continued lot cleanup.
July 13, 2003 Sunday.  A day of rest.  No work today.  Three days until demolition of the old house.  A full moon shined over the old house for the last time.
July 14, 2003 Large trees removed from rear of lot.  Removal of old concrete walkway, driveway and garage foundation.  Cut up firewood for the free pile.   Excavated a large hole on south side of  lot to cap off old clay sewer line.   Spread two loads of rock and gravel for soil erosion control.  Two days until demolition. 
July 15, 2003 One day prior to the big demolition!  No work today.
July 16, 2003

Demolition Day

The large excavator was delivered early in the morning, and demolition began around 9:30 AM with the entire house being knocked down before noon.  Brian knocked down the front of the house and then let Robert have a turn to complete the job.

The awesome power of the large machine combined with Brian and Robert's many years of experience made the whole thing look as easy as a couple of big kids playing a video game. 

The remainder of the afternoon was spent loading rubble into dumpsters and digging out the remains of the basement.

July 17, 2003 One week on the job site.  Cleaned up the last of the demolition rubble.  Some initial grading.  The last two dumpsters were picked up, along with the large excavator.  Over a dozen large green dumpsters were filled with clean green and demolition rubble in the first four days.  Four to six of the smaller white dumpsters were filled with broken concrete and bricks.   
July 23, 2003

Foundation excavation

Excavation begins.  It was decided to bring in a large bulldozer to dig the holes for the foundations.  The excavation work was sub-contracted to Albert Postema and his crew at Earthwise Excavation of Snohomish, Washington.

Once onsite, Scott of Earthwise did a great job of leveling the lot and almost completed the first foundation hole, before the bulldozer broke down and a mechanic had to be dispatched from Snohomish.   Evidently one of the tracks jammed due to skipping a tooth on one of the drive gears.  The breakdown means a second visit from Earthwise to complete what should have been a one day job.

July 25, 2003 Scott from Earthwise returned with a different bulldozer and completed the excavation of the second foundation.  The stair stepping of each foundation area reduces the amount of concrete needed to create each foundation. According to Scott, this is a common practice.  
July 25, 2003

NEW!   Bulldozer Theatre, starring Scott from Earthwise Excavation

July 28, 2003 Additional survey work to mark the exact corners of each of the two foundations.  Batter boards were installed outside the actual corners.   Survey strings are then stretched from each batter board to the next to mark the exact outline of where to build the foundation forms.
July 30, 2003 Sub contractors construct the foundation footing forms, and install the steel rebar.
July 31, 2003 Initial concrete pour to create the foundation footings.   The forms for the foundation walls will be constructed after the new concrete footings have had time to set up, followed by a second concrete pour to create the foundation walls.

The concrete was pumped into the foundation forms by Jason from Ralph's Concrete Pumping of Seattle.  Jason is the man in the blue coveralls who appears to be standing around watching the others work.  Actually, Jason is quite busy controlling the entire pumping operation from a remote control unit strapped to his waist which allows him to be right at the point of delivery.

Return to main menu


Copyright © 2003  Kevin R. McClintic.  All rights reserved.